Section: 16-00113-07-RS
Project: Resurfacing from IL State Rte 9 (1400 North Rd) to Ft Jesse Rd (1600 North Rd)
Starting Date: May 15, 2017
Status: 100% Complete
Completed August 15, 2017
Bid Cost: $1,900,601.99
Final Cost: $1,798,424.57