Colfax (In Town)

Section 18-00135-02-RS

Project: Resurfacing from Colfax Rd (CH 15) to IL State Rte 165. Work includes sidewalk ramps and curb & gutter

Start Date: May 11, 2018

Status: 100% Complete

Completion Date: June 29, 2018

Funding: MFT (Motor Fuel Tax)

Bid Cost: $629,021.24

Cost to Date: $635,475.95

Comments: Additional Sidewalk & HMA (Hot Mix Asphalt) needed to tie in existing pavement.