Section 18-00135-02-RS
Project: Resurfacing from Colfax Rd (CH 15) to IL State Rte 165. Work includes sidewalk ramps and curb & gutter
Start Date: May 11, 2018
Status: 100% Complete
Completion Date: June 29, 2018
Funding: MFT (Motor Fuel Tax)
Bid Cost: $629,021.24
Cost to Date: $635,475.95
Comments: Additional Sidewalk & HMA (Hot Mix Asphalt) needed to tie in existing pavement.