Section: 18-00053-00-FP
Project: Reconstruction & Resurfacing from Boles Ave to US Rte 24
Start Date: June 15, 2020
Status: 100% Complete
Completion Date: 11/05/2020
Funding: MFT (Motor Fuel Tax) & Matching
Bid Cost: $1,327,131.00
Cost to Date: $1,267,527.45
Comments: Project is complete. Processing final paperwork.