Section: 20-00005-05-WR
Project:
Start Date: 04/04/2022
Status: 60% Complete
Anticipated Completion Date:
Funding:
Bid Cost: $7,897,793.08
Cost to Date: $5,699,090.71
Comments: Hot-Mix Asphalt (HMA) is complete. Finishing miscellaneous work for 2022